Årjäng Northwest

The wind farm comprises 9 Vestas V112-3MW turbines.

Information about the wind farm

Startdate
Dec 2014
Yearly production
78 GWh
Total effect
27 MW
Wind turbines
9 st
Make
Vestas
  • The Årjäng Northwest wind farm comprises a total of nine wind turbines.
  • Estimated production for the nine turbines is 78 GWh annually.
  • The construction started in July 2013
  • The wind farm was in commercial operation from December 2014
  • An agreement was signed with Vestas concerning delivery of V112-3 MW
  • Civil works was conducted in partnership with Svevia, which was responsible for the construction of the infrastructure including the IKN network and the foundation of the turbines
  • Rabbalshede Kraft signed an agreement with Swedbank and SEB for bank financing in 2013
  • The County Administrative Board in the County of Värmland has in June 2012 granted an environmental permit, with the total height on 180 m, for the Årjäng Nordväst wind farm
NV1 Såviken
NV1 Såviken
Construction
01.jpg
01.jpg
02.jpg
02.jpg
03.jpg
03.jpg
04.jpg
04.jpg
05.jpg
05.jpg
06.jpg
06.jpg
07.jpg
07.jpg
08.jpg
08.jpg
09.jpg
09.jpg
10.jpg
10.jpg
11.jpg
11.jpg
12.jpg
12.jpg
13.jpg
13.jpg
14.jpg
14.jpg
15.jpg
15.jpg
16.jpg
16.jpg
Opening ceremony
Årjäng---001.jpg
Årjäng---001.jpg
Årjäng---003.jpg
Årjäng---003.jpg
Årjäng---004.jpg
Årjäng---004.jpg
Årjäng---005.jpg
Årjäng---005.jpg
Årjäng---006.jpg
Årjäng---006.jpg
Årjäng---007.jpg
Årjäng---007.jpg
Årjäng---008.jpg
Årjäng---008.jpg
Årjäng---009.jpg
Årjäng---009.jpg
Årjäng---012.jpg
Årjäng---012.jpg
Årjäng---013.jpg
Årjäng---013.jpg
Årjäng---014.jpg
Årjäng---014.jpg
Årjäng---015.jpg
Årjäng---015.jpg
Björn-Johansson.jpg
Björn-Johansson.jpg
Daniel-Schützer.jpg
Daniel-Schützer.jpg
Per-Selldén.jpg
Per-Selldén.jpg
Thomas-Linnard.jpg
Thomas-Linnard.jpg